| TB 9-2320-387-35-3
Section XVII. CABLES INSTALLATION
NOTE
If soft top has been installed, roll back to allow clearance for
routing of antenna cable in steps 17-2 through 17-5.
Lay out all cables in their approximate positions before clamps are
installed. This will minimize the length, and ensure all slack is
taken out of all cables from front of vehicle to rear.
Excess slack in all cables will be stored under EPLRS mount
assembly.
It may be necessary to drill one 0.281-in. diameter hole in left side
of antenna base bracket for antenna cable clamp. (Refer to
figure 5-62.)
17-1. Locate, mark, and drill 0.281-in. diameter hole (8) in left overhead rail (6).
17-2. Route antenna cable (9) through hole (5) in overcab mount (1) and antenna base bracket (3), and
connect to antenna (2).
17-3. Install grommet (4) in antenna base bracket (3) and overcab mount (1).
17-4. Secure antenna cable (9) to left overhead rail (6) and antenna base bracket (3) with two
loop clamps (10), two capscrews (7), two lockwashers (11), and two nuts (12).
existing screw (13).
17-6. Route antenna cable (9) to B-beam.
1
2
6
3
4
5
6
1.75
7
9
3.25
10
10
11
13
12
7
12
11 10
9
8
4.
GROMMET MS21266-4N QTY. A/R
7.
CAPSCREW B1821BH025C075N QTY. 2
9.
EPLRS ANTENNA CABLE SM-C-911480 QTY. 1
10.
LOOP CLAMP MS21333-104 QTY. 3
11.
LOCKWASHER MS35338-44 QTY. 2
12.
NUT 9419143 QTY. 2
Figure 5-61.
|