| TB 9-2320-387-35-3
NOTE
Loosen right-side tunnel insulation before performing step 17-7.
(Refer to TM 9-2320-387-24.)
17-7. Route power cable (27) under right-side tunnel insulation (28) towards terminal board. (Refer to
17-8. Attach heat shrink tubing (17) and two terminal lugs (15) and (21 to power cable negative lead (20)
and power cable positive lead (18). (Refer to TM 9-2320-387-24 for terminal connector repair.)
17-9. Connect power cable positive lead (18) to 24V terminal board (23) located on cab enclosure
panel (14) with existing nut (16).
17-10. Connect power cable negative lead (20) to ground strap (22) located on cab enclosure panel (14)
with existing nut (16). Secure leads together with tiedown strap (19).
17-11. Secure right-side tunnel insulation. (Refer to TM 9-2320-387-24.)
15
16
17
18
14
~
19
23
22
16
21
17
25
15.
TERMINAL LUG 7728780 QTY. 1
17.
SHRINK TUBING MS23053/4-302-0 QTY. A/R
19.
TIEDOWN STRAP MS3367-1-0 QTY. A/R
21.
TERMINAL LUG 7728777 QTY. 1
Figure 5-63.