| TB 9-2320-280-35-5
Section XII. PLGR BRACKET INSTALLATION
12-1. Install PLGR bracket (11) on integrated rack (1) with four screws (12).
12-2. Locate, mark, and drill one 0.201-in. diameter hole (9) in right side engine tunnel (10).
12-3. Remove paint from vicinity of hole (8) on integrated rack (1) and hole (9) on right side engine
tunnel (10). Apply antiseize compound as required.
12-4. Fabricate ground strap (4) from 8.00-in. length of braided wire and two terminal lugs.
12-5. Install ground strap (4) on integrated rack (1) with capscrew (5), three lockwashers (2), and nut (3).
12-6. Install ground strap (4) on right side engine tunnel (10) with self-tapping screw (7) and two
lockwashers (6).
4
2
5
6
7
3
8
2
1
9
~
10
11
2. LOCKWASHER MS45904-68 QTY. 3
3. NUT 9419143 QTY. 1
12
4. GROUND STRAP
BRAIDED WIRE AA59569F30T0375 QTY. A/R
TERMINAL LUG MS20659-129 QTY. 2
5. CAPSCREW B1821BH025C100N QTY. 1
6. LOCKWASHER MS35338-43 QTY. 2
7. SELF-TAPPING SCREW 9426241 QTY. 1
11. PLGR BRACKET 986-0645-001 QTY.
1
12. SCREW MS35206-263 QTY. 4
Figure 5-29.
|