NOTE
Remove and discard four existing bolts from left and right
B-pillars before performing steps 17-7 through 17-10.
17-7. Remove paint from vicinity of four holes (12) on left side of vehicle B-pillar. Apply antiseize
compound as required.
17-8. Install left overhead rail (8) on left B-pillar mounting (13) with four capscrews (14) and
washers (15). Do not tighten capscrews.
8
12
15
13
14
Figure 5-57.
17-9. Remove paint from vicinity of four holes (17) on right side of vehicle B-pillar (16). Apply antiseize
compound as required.
17-10. Install right overhead rail (9) on right B-pillar mounting (16) with four capscrews (14) and washers
(15). Do not tighten capscrews.
9
17
14
14. CAPSCREW B1821BH025C138N QTY. 8
15
16
15. WASHER 2436161 QTY. 8
Figure 5-58.
|