Page Title: INSTALLATION PROCEDURES
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



TO 31R2-2GRC171-2
TM 11-5820-815-14
NAVELEX 0967-LP-544-5010
SECTION III
INSTALLATION PROCEDURES
2-19. MOUNTING.
NOTE
2-20.
RADIO RECEIVER-TRANSMITTER
Do not secure unit until after initial setup has
RT-980/GRC-171.
been performed.
2-21.  The RT-980/GRC-171 mounts in a standard
f. Slide unit into rack and secure with four screws
482.6-mm (19-in) rack cabinet. The unit requires 222.3
and flat washers provided by the user.
mm (8.75 in) of vertical clearance and 546.1 mm (21.50
in) of front-to-rear clearance as shown in figure FO-1.
2-22.
RADIO SET CONTROL C-7999/GRC-171.
To mount the unit, proceed as follows:
2-23.  The
C-7999/GRC-171
maybe
mounted
anywhere within 305 m (1000 ft) of the RT-980/GRC-
NOTE
171. Refer to paragraph 2-14 for cable requirements.
The mounting space required by the front panel is 82.6
Slide rails are attached to the RT-980/ GRC 171
mm (3.25 in) wide by 66.7 mm (2.62 in) high as shown in
at the factory. The cabinet mounted slides are
figure 2-1. Front-to-rear clearance required allowing for
contained in slide mounting hardware kit, Collins
the mating connector is at least 152.4 mm (6.00 in). To
part number 623-5818-001. Inventory the slide
mount the C-7999/ GRC-171, proceed as follows:
mounting hardware kit using figure FO-1 prior to
installing the kit.  The kit contains four slide
brackets designated as front left, front right, rear
NOTE
left, and rear right.  The brackets are easily
identified  by  comparing  the  part  number
stamped on each bracket with figure FO-1.
The C-7999/GRC-171 is designed to mount in an
existing user-supplied panel.
If it should be
a. Mount slides in cabinet using hardware provided.
necessary to cut a mounting hole, refer to panel
Refer to figure FO-1.
mounting detail of figure 2-1 for dimensions. Drill
screw holes for 4-40 tap or use #27 clearance drill.
b. Install RT-980/GRC-171 on slides in cabinet.
a. Connect mating connector to J1 at rear of unit.
c. Install ground wire on lug provided at rear of unit.
b. Fasten unit in place with four 4-40 roundheaded
screws and lockwashers.
CAUTION
2-24.
INITIAL SETUP PROCEDURE.
Do not apply primary power to unit until after
2-25.  The initial setup procedures ensure that the RT-
checking primary power strapping.  Refer to
980/GRC-171 matches the operational requirements of
primary power strapping, para- graph 2-26 and
the user station. There are no initial setup procedures
for the C-7999/GRC-171.
d. Connect cables to A100A2J6, A100J7, A100A2J8
CAUTION
(if used), A10A2J9, and A10A2J22 at rear of unit.
Do not apply primary power to the RT-980/ GRC-
e. At front panel, verify that the coaxial jumper is
171 until primary power strapping has been
connected between ANT and XCVR jacks.
checked. Refer to paragraph 2-26 and figure 2-2.
2-5