| TM 11-5820-554-12
ELOD0025
Figure 9-1. Regulator, Voltage CN-1214/G ,front panel view.
Section II. INSTALLATION
that will provide adequate ventilation, and connecting
9-5. Tools and Equipment Required for
the input and output cables. Perform the operations
Installation
listed below.
CAUTION
The tools and equipment required for installation of
Provide ventilation for the unit to insure
Regulator, Voltage CN-1214/G are listed below.
adequate heat dissipation.
Avoid
a. Tools. Tool Kit, Electronic Equipment
installing the unit close to heat-producing
TK101/G.
equipment such as space heaters.
a. Hoist the regulator out of the shipping carton,
and lower it onto a bench; use a chain hoist attached to
9-6. Installation Procedure
the four eyebolts on the top.
b. Locate the regulator on the bench in accordance
The installation of Regulator, Voltage CN-1214/G
with minimum clearances (fig. 9-2)
consists only of removal of the equipment from the
shipping box and hoisting it into a position on a bench
9-7. Controls and Indicators (fig. 9-3)
Control
Function
Circuit breaker ............................................................................................... Used to turn unit on and off; provides overload protection.
OUTPUT VOLTAGE control ........................................................................ Used to set the desired output voltage.
LINE pilot light (amber) ................................................................................ Indicates when unit is energized
CONTROL circuit fuse.................................................................................... Control circuit protection.
9-2
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |