Section XVI. PLGR POWER CABLE INSTALLATION
16-1. Route PLGR power cable (2) from PLGR assembly (1) to B-beam (3).
1
2
~
13
2
2. PLGR POWER CABLE 9728558-10 QTY. 1
Figure 5-68.
16-2. Attach shrink tubing (7) and terminal lugs (5) and (11) to PLGR power cable negative lead (10) and
PLGR power cable positive lead (8). (Refer to TM 9-2320-387-24 for terminal connector repair.)
16-3. Attach PLGR power cable positive lead (8) to 24-volt terminal board stud (4) with existing nut (6).
16-4. Attach PLGR power cable negative lead (10) to ground strap stud (12) with existing nut (9).
5
6
7
4
8
11
12
7
10
9
5. TERMINAL LUG 7728780 QTY. 1
7. SHRINK TUBING MS23053/4-302-0 QTY. A/R
11. TERMINAL LUG 7728777 QTY. 1