2-4. TEST METER TESTS.
PURPOSE
The test meter tests provide an overall performance check of the radio set. Test switch S9801 selects
various operating voltages in the receiver-transmitter and applies them to test meter M9601.
TEST EQUIPMENT AND MATERIALS
Power Supply PP-2953/U
Maintenance Kit MK-1035/ARC-131
All cables ore part of MK-1035/ARC
TEST SETUP
Connect equipment as shown in test setup diagram. Turn on all equipment and allow at least 5 minutes
for warmup.
EL1AT140
INITIAL EQUIPMENT CONTROL SETTINGS
Set equipment controls as indicated in the following table.
CONTROL AND SWITCH SETTINGS
POSITION/SETTING
CONTROL OR SWITCH
EQUIPMENT
TEST SWITCH
Set as instructed in
RT-8231ARC-131
procedures.
XMTR HI-LO
HI
2-4
|